Time & Work Worksheet-2
-
A and B can do a piece of work in 72 days; B and C can do it in 120 days; A and C can do it in 90 days. In what time can A alone do it?
(a) 80 days (b) 100 days (c) 120 days (d) 150 days
-
A and B can do a piece of work in 5 days; B and C can do it in 7 days; A and C can do it in 4 days. Who among these will take the least time if put to do it alone?
(a) A (b) B (c) C (d) Data inadequate
-
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
(a) 8 hours (b) 10 hours (c) 12 hours (d) 24 hours
-
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
(a) 15 days (b) 20 days (c) 25 days (d) 30 days
-
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work is:
(a) 4 days (b) 6 days (c) 8 days (d) 18 days
-
A is twice as good a workman as B and together they finish a piece of work in 14 days. The number of days taken by A alone to finish the work is:
(a) 11 (b) 21 (c) 28 (d) 42
-
A is thrice as good a workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
(a) 20 days (b) days (c) 25 days (d) 30 days
-
A and B can do a job together in 7 days. A is times as efficient as B. The same job can be done by A alone in:
(a) days (b) 11 days (c) days (d) days
-
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
(a) 15 (b) 16 (c) 18 (d) 25
-
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
(a) 11 days (b) 13 days (c) days (d) None of these
-
A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it?
(a) 30 days (b) 35 days (c) 40 days (d) None of these
-
A is 50% as efficient as B. C does half of the work done by A and B together. If C alone does the work in 40 days, then A, B and C together can do the work in:
(a) days (b) 15 days (c) 20 days (d) 30 days
-
Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked as efficiently as he actually did, the work would have been completed in 3 days. A alone could complete the work in:
(a) days (b) days (c) days (d) None of these
-
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is:
(a) (b) (c) (d)
-
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(a) 5 (b) (c) 6 (d) 8
Answer Key:
(1)-c; (2)-a; (3)-c; (4)-c; (5)-a; (6)-b; (7)-b; (8)-b; (9)-b; (10)-b; (11)-a; (12)-a; (13)-b; (14)-d; (15)-c